The solution
To meet these requirements, Vale selected Metso’s FIT™ station technology—a modular, ready-to-install solution that reduces risk, shortens implementation time, and ensures quality.
Three new modular crushing stations were designed and delivered, creating an intermediate stage between existing primary and secondary crushing. The entire process—design, procurement, manufacturing, and delivery—was completed in nine months, compared to the usual 14 months for traditional approaches.
“Modularization is something we strive for at Vale. It reduces people’s exposure to risk, shortens implementation time, and brings more quality and efficiency to operations,” says Anderson Gomes, General Manager of Implementation at Vale.
According to Luiz Otávio Arantes, Vale's Engineering Manager, three factors were decisive:
- Pre-engineered design, simplifying planning.
- Modularization, drastically reducing assembly time.
- Safety, with a solution validated by Metso.
“The FIT station is a new technology with a key-and-skid system, fully modularized and implemented in an extremely short timeframe,” says Roberto Nascimento, Master Project Engineer at Vale.
The configuration included GP500 crushers, screens, and conveyors, totaling 1,200 tons. Two stations were installed in a stacked arrangement to maximize limited space. Skid-mounted bases eliminated traditional civil foundations, enabling completion within 94 days, including commissioning and start-up.